Jiangsu LNG Project became
operational |
PetroChina Jiangsu LNG Project
started trial operation when its first cargo of LNG was
delivered by a carrier named "Al Rekayyat" that smoothly
berthed at the dedicated Jiangsu LNG jetty on May 24,
2011.
With the LNG cargo from Qatar, this Q-Flex
carrier is the world's second largest LNG vessel and the
largest LNG carrier ever been received in China. Its
315-meter long and 50-meter wide hull can carry 216,000
cubic meters in full capacity or 145,000 cubic meters of
LNG when half loaded. PetroChina Jiangsu LNG Project has
a maximum unshipping capacity of 267,000 cubic meters,
the largest in the world.
|
 |
About the
Project |
|
Located in the Western Solar Sand
("Xitaiyangsha") sea area, 14 kilometers offshore
in Rudong county of Jiangsu Province, the Jiangsu
LNG Project is composed of the artificial island,
receiving terminal, pierhead trestle and
sea-crossing pipeline. It mainly receives, stores,
gasifies, and transports overseas LNG. The Project
is connected to the West-East Gas Pipelines and
the Ji-Ning branch through gas trunks. It secures
gas supply as one of multiple gas sources that
complement to and run as standby for each
other.
The two-phase Project was commenced
in January 2008. Its first phase already completed
can receive 3.5 million tons and supply 4.8
billion cubic meters of gas per year, and can
provide ten days of peak shaving gas accommodation
for the West-East Gas Pipeline. The second phase
is planned to become commissioning at the end of
2013, which will boost the annual receiving
capacity to 6.5 million tons and gas
deliverability to 8.7 billion cubic meters. The
project will have a long run capacity of 10
million tons and 13.5 billion cubic meters
respectively.
|
Receiving
Terminal
Jiangsu LNG Receiving
Terminal is composed of facilities for the
unloading, storage and gasification of LNG, and
the metering and output of natural gas. Its
3.5Mt/a capacity for the first phase is provided
by three 160,000 cubic meters full-capacity
low-temperature tanks, two of which have been
started on an earlier stage, three open rack
vaporizers (ORVs), three submerged combustion
vaporizers (SCVs), three 20" unloading arms and
one return arm. The second stage will introduce an
ORV and a SCV to boost the capacity to 6.5Mt/a.
Moreover, a 10Mt/a capacity is allowable in the
long run. The Φ1,016mm unloading trunk at the
terminal is 1,970 meters long, the thickest and
second longest in the world.
|
 |
Pierhead
Trestle
A 1,970m-long pierhead
trestle connects the 430m-long jetty to the
artificial island of the receiving terminal in the
Jiangsu LNG Project, which can receive 6 million
tons of LNG per year. The trestle is the longest
one for LNG unloading in China, and the second
longest in the world, next to only the LNG
unloading trestle at Dahej terminal of India. It
consists of ten compensator piers, nine anchor
piers, and twenty steel trestle sections. Each
section has a calculated length of 86.8 meters and
a width of 12.5 meters, with the maximum truss
height of 11.5m at the middle point of each span
and the weight of each section about 350 tons. The
jetty consists of one working platform, four
mooring dolphins, six bollards, and a ten-section
steel trestle for pedestrians. The jetty can berth
LNG carriers with a capacity ranging from 80,000
cubic meters to even the highest of 267,000 cubic
meters in the world.
|
 |
Sea-crossing Pipeline
The sea-crossing pipeline consists
of a normal section, a sea-crossing bridge
section, and an off-take station. The 19km-long
pipeline is 1,016mm in diameter and 26.2mm in wall
thickness, and can transport 10 million tons (13.5
billion cubic meters) of gas per year.
The
pipeline was completed on June 15, 2011. It has a
10,763-meter-long sea-crossing section, longer
than any other sea-crossing gas pipeline in the
world, and registers the first of long-span
pipeline construction. |
 |
|
 |
Milestones |
2001
● On
November 1, PetroChina and the People's Government
of Jiangsu Province signed the Memorandum of LNG
Cooperation.
|
2005
● On
March 12, PetroChina and the People's Government
of Jiangsu Province signed the Cooperative
Agreement of Jiangsu LNG Project in Beijing.
|
2007
● On
January 19, construction of the artificial island
as part of Jiangsu LNG Project formally
commenced.
● On November 15, the receiving
terminal block as part of Jiangsu LNG Project was
successfully reclaimed.
|
2008
● On
April 13, the pile foundation test of tanks as
part of Jiangsu LNG Project formally commenced.
● On May 20, the pile foundation test of tanks
as part of Jiangsu LNG Project was successfully
completed on schedule.
● On June 29,
construction of the seawall on the artificial
island as part of Jiangsu LNG Project was
completed.
● On October 28, the jetty for heavy
pieces and working boats, an infrastructural
support for the construction and operation of
Jiangsu LNG Project, was completed.
|
2009
● On
March 6, tank installation of Jiangsu LNG Terminal
was kicked off.
● On March 12, the Joint
Venture Contract of Jiangsu LNG Project was
concluded in Beijing. The Project is jointly built
and operated by PetroChina, Pacific Oil & Gas,
and Jiangsu Guoxin Investment Group Limited. The
three parties hold 55%, 35%, and 10% in the equity
of the JV, respectively.
● On April 7, the
first piece of tank vault of Jiangsu LNG Project
was prefabricated and hoisted to place.
●In
October 6, the vault for the first 160,000 cubic
meters LNG1 tank of Jiangsu LNG Project was
pneumatically jacked to the top of the tank.
|
2010
● On
September 28, the second tank of Jiangsu LNG
Terminal was installed and the hydraulic test was
started.
|
2011
● On
May 24, Jiangsu LNG Project was successfully put
into trial operation.
|
|
|
|
|