Dalian LNG Terminal becomes
trial operational |
| On November 16, Dalian LNG
Terminal welcomed its first LNG carrier "Expedient",
indicating that the trial operation of Dalian LNG
project is formally
commenced. |
 |
Project
Introduction |
|
 |
Located on the Dagushan peninsula in Dalian
city, Liaoning province, Dalian LNG Terminal
covers an area of 21.6 hectares. Independently
designed, procured, constructed and managed, the
project boasts the most advanced technology, most
complete functions, highest domestic manufacture
rate, minimum site area and lowest investment in
China. With functions including LNG unloading,
storage, gasification, external transportation,
and tanker loading, Dalian LNG terminal is China's
only LNG terminal with loading
capacity.
Construction of Dalian LNG
project was started in April 2008 and completed in
April 2011. The project is composed of a dock,
receiving terminals and gas pipelines. The first
phase of the receiving terminal has a construction
scale of 3 million tons per year and designed
annual deliverability of 4.2 billion cubic meters.
The second phase will have a construction scale of
6 million tons per year and designed annual
deliverability of 8.4 billion cubic meters. When
the whole project is completed, the terminal will
be capable of receiving 10 million tons and
deliver 13.5 billion cubic meters every
year. |
Dalian's LNG sources are mainly from Qatar,
Australia and Iran. After gasification at the
terminal, natural gas supply can be connected to
China's northeastern and northern pipeline
networks through the pipeline from Dalian to
Shenyang, to cover Northeast China and part of
North China.
|
Dock
The dock
has a total length of 446 meters, including a 150
meters long trestle. The largest open LNG terminal
in China, it is capable of parking the world's
biggest LNG carrier. Construction of the dock was
started on March 1, 2009, and completed on August
29, 2010.
|
Terminal
There are
three storage tanks in the LNG project, each with
a storage capacity of 160,000 cubic meters, making
the effective storage capacity totaling 480,000
cubic meters. 84 meters in diameter and 51 meters
in height, each storage tank can actually store
160,000 cubic meters of LNG at an ultra-low
temperature of minus 162 degrees Celsius.
|
Pipelines
In
the short term, Dalian LNG terminal will serve as
the major gas supply source for Liaoning province
and secure gas supply in Northeast China and the
Bohai rim region. Whereas in the long term, it
will be connected to Shaan-Jing gas pipeline,
Northeast gas pipeline, Russia-China gas pipeline,
North China underground gas storage, and Tangshan
LNG project, to form a complementary gas supply
pattern that enjoys multiple supply
sources. |
|
 |
Milestones |
● Land formation project broke ground in
Dagushan peninsula, Dalian, initiating the large
scale construction of Dalian LNG project.
●
April 18, 2008, Construction of Dalian LNG project
started.
● March 1, 2009, Dock of Dalian LNG
project started to be constructed.
● March 16,
Installation of the storage tanks started.
●
August 29, 2010, Construction of the dock
completed.
● April, 2011, The whole project
was completed.
● November 16, 2011, Dalian LNG
project became trial operational. |
 |
|
|
|
|