Phase II boosting project of Samandepe gas field becomes operational
2018/11/05

On October 29, the Phase II boosting project of Samandepe gas field of Block A in the Bagtyiarlyk Contract Area of CNPC Amu Darya River Company became operational.

The project was started on December 30, 2016. It includes the construction of one booster station, the renovation of two gas gathering stations and the construction of linking pipelines. Four gas-driven reciprocating compressors were newly added, boosting the total installed capacity to 43 MW and increasing the feed gas by 6,500,000 cubic meters per day.